New national planning fees apply in England from 8 December 2026. The fee is the one in force on the day you submit, not the day you start design.

ApplicationBefore 8 Dec 2026From 8 Dec 2026Typical time
Householder planning (extensions, alterations)£548£5758-week target; allow about 13 weeks including validation
Lawful Development Certificate (permitted development)£274£287.50No statutory deadline; about 10 weeks is typical
Prior approval: larger home extension£249£31042-day determination

Typical decision times: householder planning has an 8-week target (allow about 13 weeks including validation); a Lawful Development Certificate has no statutory deadline (about 10 weeks is typical); prior approval is decided within 42 days.

England only. Check your local planning authority's website for the current fee before you submit. Wales and Scotland set their own fees.

What it means for your timeline

If design starts now, most applications will go in after 8 December 2026 and pay the new fee. Typical design time from measured survey to submission is 6–8 weeks. Allow for validation (1–2 weeks) before the council's clock starts.

Which route do you need?

Your Architect will confirm the right route for your site.

Fees on top of planning

Budget separately for Building Control (typically £800–£1,500), a build-over agreement if you build near a public sewer (£400–£1,000), and party wall surveyors on attached houses.