How to compare builder quotes like-for-like

Three quotes for the same extension can differ by tens of thousands of pounds, and the lowest headline price is often the one that has left the most out.

Why quotes are hard to compare

Five steps to a fair comparison

  1. Send every builder the same schedule of works, based on your Architect's drawings and specification.
  2. Put each builder's price against each line. Mark anything excluded, TBC or missing.
  3. Add the missing items back at a budget rate, so every total covers the same work.
  4. Compare including VAT, since a builder who isn't VAT registered can be genuinely cheaper.
  5. Check the builder, not just the price: insurance, an insurance-backed guarantee, references and fair stage-payment terms.

A typical example

In our sample 25 m² extension, the quote with the lowest headline price (£59,170 ex-VAT) had left out nine items worth about £24,775 at budget rates. Once those were added back, it ranked second, and a quote £11,620 higher on the headline was the best like-for-like value.

Never pay ahead of the work

Agree stage payments tied to inspected milestones (foundations approved, walls to wall-plate, roof on, first fix, plaster) with a small retention held until the end of the defects period. Get every change priced and signed before the work is done.